Construction progress in November
First we had to do the earthworks. The supposedly flat meadow was 2 meters sloping, so that earth had to be removed and refilled (approx. 7000 cubic meters). The earth material also had to be stabilized: The crushed-stone base was placed (approx. 120 trucks).
After the terrain (about the size of a football field) had been prepared, we could begin with the foundation work. The 52 individual foundations for the reinforced concrete columns of the supporting structure are currently being constructed. For the foundations, approx. 500m³ of earth will be excavated. Approx. 30 trucks of concrete are being poured. The 240 precast concrete elements will be produced in the meantime in the production halls of Traub in Ebnat.